Triple ‘M’ was engaged by Leighton Contractors to provide the Mechanical Services for this totally new hospital. The old hospital HVAC system was kept operational by Triple’M’ until completion and commissioning of the new building.
Many innovations are featured in this state of the art facility, and we are justifiably proud to have been an integral part in the provision of such a valuable health asset for Western Sydney Health.
| Sector: | Health Care |
| HVAC Value: | $ 8 million |
| Developer: | NSW Department of Health |
| Head Contractor: | Leighton Contractors |
| HVAC Design: | Triple ‘M’ Design and Construct based on Steensen Varming concept design. |
| Completion date: | March 2000 |
| System type: | Chilled water variable air volume, plus medical gasses. The project included the installation of three new chillers and two new boilers, and dedicated systems for the operating theatres. |